Question: EX5-3 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percents. If the total project cost is

EX5-3 (Algo) Below is a project WBS with cost...

EX5-3 (Algo) Below is a project WBS with cost... Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $597,000, what are the estimated costs for the following deliverables? (Round the final answer to the nearest dollar.) Router systems project 597000 Definition Design 6% 43% Objectives Requirements Inputs Outputs Files Interfaces Programming in-house testing 3% 3% 4% 4% 4% 11% 20% 40% Implementation 51% Customer testing and review 11% a. Design? b. Programming? c. In-house testing