Question: Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks

Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks Compute the task variance. A. 0.69 OB. 0.5 C. 2.25 O D. 4.17 E. 1.23