Question: Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks

Following are the three time estimates for a task in a project:
optimistic completion time =2 weeks
most likely completion time =4 weeks
pessimistic completion time =7 weeks
Compute the task variance.
0.5 weeks
1.23 weeks
0.69 weeks
2.25 weeks