Question: Three time estimates for a task in a project are as follows: Optimistic completion time =6 weeks Most likely completion time =12 weeks Pessimistic completion

Three time estimates for a task in a project are as follows: Optimistic completion time =6 weeks Most likely completion time =12 weeks Pessimistic completion time =16 weeks Calculate the expected task completion time. The expected task completion time is weeks. (Enter your response rounded to one decimal place.)