Question: Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks
-
Following are the three time estimates for a task in a project:
optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks
Compute the expected time for the task.
3.5 weeks
4.167 weeks
5.23 weeks
5.75 weeks