Question: Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks

  1. Following are the three time estimates for a task in a project:

    optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks

    Compute the expected time for the task.

    3.5 weeks

    4.167 weeks

    5.23 weeks

    5.75 weeks