Question: Given a simple project illustrated in the following table immediate Time Activity Predecessors (weeks) 1 2 2 3 3 11, 2 2 4 3 5

Given a simple project illustrated in the
Given a simple project illustrated in the following table immediate Time Activity Predecessors (weeks) 1 2 2 3 3 11, 2 2 4 3 5 5 4 4 Nw The required project completion time is 14. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"? 7 00 9 10