Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic Most Likely Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path we have a Path Mean and a Path Standard Deviation For Path we have a Path Mean and a Path Standard Deviation Determine both the Probability that Path will finish in Days or Less and the Probability that the Project will finish in Days or Less.
:
:
:
:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
