Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 27 and a Path Standard Deviation = 3. For Path 1-3-4-5 we have a Path Mean = 26 and a Path Standard Deviation = 3. Determine both the Probability that Path 1-2-5 will finish in 27 Days or Less and the Probability that the Project will finish in 27 Days or Less.
Question options:
| A | 0.5 : 0.315279298 |
| B | 0.977249938 : 0.96765793 |
| C | 0.747507533 : 0.628911531 |
| D | 0.990184693 : 0.986391865 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts