Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 4 3

Given is a CPM project network diagram as shown below. Given is a CPM project network diagram as shown

Activity

Start

A

B

C

D

E

F

G

H

End

day

0

4

3

7

5

2

5

8

4

0

a) The Project Completion time = ________ days. b) The Earliest Start time, ES, of Activity G = _________ days. c) The Latest Finish time, LF, of Activity C = __________ days. d) The critical activities are = _________ (ex. Fill in answer as: ABCD)

A F. Start E . End B B D D G