Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6

Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
day
0
5
6
9
6
9
8
5
4
0
a) The Project Completion time =? days.
b) The Earliest Start time, ES, of Activity G =?days.
c) The Latest Finish time, LF, of Activity C =? days..
d) The critical activities are =?(ex. Fill in the answer as: ABCD)