Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 9

  1. Given is a CPM project network diagram as shown below.

    Activity

    Start

    A

    B

    C

    D

    E

    F

    G

    H

    End

    day

    0

    5

    9

    4

    7

    4

    8

    6

    8

    0

    a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)