Question: Given is a CPM project network diagram as shown below. C F H H Start E End B D G Activity Start 2 B 6

Given is a CPM project network diagram as shown
Given is a CPM project network diagram as shown below. C F H H Start E End B D G Activity Start 2 B 6 8 D 3 E 4 F 2 G 3 H 2 End 0 days 0 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are - (ex. Fill in answer as: ABCD)