Question: Given the following data: Activity Predecessor Duration (days) a - 10 b - 15 c a 17 d b 5 e b 4 f c

Given the following data:
Activity Predecessor Duration (days)
a - 10
b - 15
c a 17
d b 5
e b 4
f c 15
g d 7
h e 8
i f 12
j g,h,i 10
1) Draw the network (AON) and calculate the Critical Path.
2) Your organization has been appointed to co-ordinate the local government elections.
Develop a Work Breakdown Structure (WBS) graphical format for this project.