Question: Given the following information about a small project, Task Duration Immediate Estimates Predecessors A 2 days None B 5 days A C 8 days B
Given the following information about a small project,
Task Duration Immediate
Estimates Predecessors
A 2 days None
B 5 days A
C 8 days B
D 7 days A
E 3 days B & D
F 3 days E & C
- Draw a network diagram.
- Identify the critical path, earliest start and finish and slack for each task.
- Using MS Excel, produce a Gantt chart for this project.
- What would happen if a new estimate for task D increases its expected duration from seven days to fourteen days? Would the project take longer? Would anything else change?