Question: Given the following information about a small project, Task Duration Immediate Estimates Predecessors A 2 days None B 5 days A C 8 days B

Given the following information about a small project,

Task Duration Immediate

Estimates Predecessors

A 2 days None

B 5 days A

C 8 days B

D 7 days A

E 3 days B & D

F 3 days E & C

  1. Draw a network diagram.
  2. Identify the critical path, earliest start and finish and slack for each task.
  3. Using MS Excel, produce a Gantt chart for this project.
  4. What would happen if a new estimate for task D increases its expected duration from seven days to fourteen days? Would the project take longer? Would anything else change?Given the following information about a small
Given the following information about a small project, Task Duration Immediate Estimates Predecessors 2 days None B 5 days A n 8 days B D 7 days A E 3 days B&D F 3 days E & C a. Draw a network diagram. b. Identify the critical path, earliest start and finish and slack for each task. c. Using MS Excel, produce a Gantt chart for this project. d. What would happen if a new estimate for task D increases its expected duration from seven days to fourteen days? Would the project take longer? Would anything else change

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!