Question: Given the following information about a small project, Task Duration Immediate Estimates Predecessors A 12 days None B 8days None C 5 days None D
Given the following information about a small project,
Task Duration Immediate
Estimates Predecessors
A 12 days None
B 8days None
C 5 days None
D 10 days A & B
E 10 days C & D
F 5 days A & B
Draw a network diagram.
Gantt chart