Question: Given the following project information: table [ [ , Start,Finish,Duration Estimate ( Days ) ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ] , [

Given the following project information:
\table[[,Start,Finish,Duration Estimate (Days)],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,9,15,21],[B,1,3,13,21,23],[C,2,4,6,9,18],[D,2,5,23,35,47],[E,3,5,19,26,27],[F,4,6,23,29,41],[G,5,6,14,20,26],[H,6,7,2,5,8]]
Determine:
a. Critical path
 Given the following project information: \table[[,Start,Finish,Duration Estimate (Days)],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,9,15,21],[B,1,3,13,21,23],[C,2,4,6,9,18],[D,2,5,23,35,47],[E,3,5,19,26,27],[F,4,6,23,29,41],[G,5,6,14,20,26],[H,6,7,2,5,8]] Determine: a.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!