Question: Given the following tasks, what is the float on the critical path? Task Predecessor Duration A --- 7 B A 6 C B 7 D
Given the following tasks, what is the float on the critical path? Task Predecessor Duration A --- 7 B A 6 C B 7 D A,C 8
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts