Question: Given the project within the table below, calculate the following: Activity Predecessor Time (days) A 7.5 B 9.7 C 10.5 D 8.8 E 10 F

Given the project within the table below, calculate the following: Activity Predecessor Time (days) A 7.5 B 9.7 C 10.5 D 8.8 E 10 F 4.2 G 9.7 H G 11.5 a. What is the project length? [ Select ] b. What activities are on the critical path? [Select ] c. How much slack is in activity A? [ Select] and activity B? [ Select] LL A, C D B, E TI F