Question: i just need d) and e) Given the project within the table below, calculate the following: Activity Predecessor Time (days) 2.5 B 3.7 7.5 D

i just need d) and e) i just need d) and e) Given the project within
i just need d) and e) Given the project within
Given the project within the table below, calculate the following: Activity Predecessor Time (days) 2.5 B 3.7 7.5 D AC 8.8 E D 10 F BE 4.2 G F 9.7 H G 11.5 a. What is the project length? [Select) b. What activities are on the critical path? Select] c. How much slack is in activity A? Select | and activity G? [Select) d. What is the Late Start / Late Finish for activity E? [ Select e. What would happen to the overall project length if activity A was delayed by 6 days, now taking a total of 8.5 days? [Select]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!