Question: Given the project within the table below, calculate the following: Activity Predecessor B Time (days) 2.5 3.7 7.5 8.8 10 C , E D F

Given the project within the table below,
Given the project within the table below, calculate the following: Activity Predecessor B Time (days) 2.5 3.7 7.5 8.8 10 C , E D F BE 4.2 F G H 9.7 11.5 G a. What is the project length? Select] b. What activities are on the critical path? [Select] c. How much slack is in activity A? [Select] and activity G? [Select ] d. What is the Late Start / Late Finish for activity E? [Select) e. What would happen to the overall project length if activity A was delayed by 6 days, now taking a total of 8.5 days? [Select]