Question: he critical path for the network activities shown below is ________ with duration ________. Activity Duration ImmediatePredecessors A 6 -- B 2 -- C 6
he critical path for the network activities shown below is ________ with duration ________. Activity Duration ImmediatePredecessors A 6 -- B 2 -- C 6 A, B D 1 A, B E 2 B, C, D Question 5 options: 1) B