Question: Q20: The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 10 --- B 8 --- C
Q20:
The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 10 --- B 8 --- C 2 A D 4 A E 5 B,C,D
a.
none of the choices are correct
b.
A-D-E; 18
c.
A-D-E; 19 & A-B-D; 19
d.
B-E; 13
e.
A-B-C-D-E; 29
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
