Question: In making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M, P, and T. The
In making a backward pass through a network, activity L has an activity time of 6 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 32, 27, and 26, respectively. The late finish times for activities M, P, and T are 39, 37, and 33, respectively. What is the late start time for activity L?
a. 33
b. 22
c. 20
d. 13
e. 17
Step by Step Solution
There are 3 Steps involved in it