Question: In the below chart, which is the critical path Name Predecessor Duration A - 6 B A 3 C A 4 D B 2 E

In the below chart, which is the critical path
Name Predecessor Duration
A -6
B A 3
C A 4
D B 2
E C 21
F D, E 1
Group of answer choices
A-B-D-F
A-C-E-F