Question: Job Processing time ( Days ) Job Due Date ( Days ) A 1 9 2 8 B 1 8 2 1 C 3 8
Job Processing time Days Job Due Date Days A B C D E There are painting jobs awaiting at a paint shop. Their processing times and due dates are shown in the table. The firm wants to determine the sequence of jobs according to shortest processing time SPT Jobs are assigned a letter in the order day arrived. What is the average job lateness Today is day and work begins today. Round your final answer to two decimal places. Do not enter any units. Only enter a number without any units.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
