Question: ob J is currently awaiting processing at WC202. J will require 8 hours of processing time at WC202. After WC202, J will have process requirements
ob J is currently awaiting processing at WC202. J will require 8 hours of processing time at WC202. After WC202, J will have process requirements of ...
8 hours at WC504
6 hours at WC603
13 hours at WC429
Standard move/queue time is calculated at 5 hours per work center.
If Job J is due 52 hours from now, what is J's Critical Ratio? (Round to 2 decimal places)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock