Question: Please fill the below blanks. A - E - G (critical path) / 14 days if it's critical path draw O in the blanks. Thanks

Please fill the below blanks.

A - E - G (critical path) / 14 days

if it's critical path draw O in the blanks.

Thanks in advance!

Please fill the below blanks. A - E - G (critical

\begin{tabular}{|c|c|c|} \hline activitiy & precedessor & durations \\ \hline A & none & 5 \\ \hline B & none & 4 \\ \hline C & none & 2 \\ \hline D & A & 3 \\ \hline E & A, B, C & 6 \\ \hline F & C & 7 \\ \hline G & D, E, F & 3 \\ \hline \end{tabular}