Question: PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: What is the

PM.53 Sun Oracle is launching a new computer

PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: What is the duration of the project? weeks What is the latest start week for activity C ? What is the slack time for activity F? weeks If activity E were shortened by 5 weeks, what would be the new duration of the project? weeks