Question: Prepare a master production schedule based on the following information: Beginning inventory: 145 Schedule production whenever projected-on-hand drops below 20. Production lot size is 250
Prepare a master production schedule based on the following information:

Beginning inventory: 145
Schedule production whenever projected-on-hand drops below 20.
Production lot size is 250 units.
Week: Forecast Orders 1 100 106 2 100 3 120 4 120 40 5 150 21 6 150 9 7 180 2 8 180 0 94 65 9Step by Step Solution