Question: Problem 5-8 (Algo) Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY B D E A A B C D TIME (WEEKS) 3 4 6
Problem 5-8 (Algo) Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY B D E A A B C D TIME (WEEKS) 3 4 6 1 4 3 1 2 F EG b. What is the critical path? O A-C-E-F-G-H O A-B-D-F-G-H O A-C-Et O A-B-D-E-H c. How many weeks will it take to complete the project? Number of weeks