Question: Project B You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.
Project B
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.
Calculate ETC, EAC and VAC.
Budget $220,000
Duration 200 days
Status 140 days
EV $180,000
PV $180,000
AC $220,000
BAC ?
Assume that the same spend rate continues for the rest of the project.
1) ETC =
2) EAC =
3) VAC =