Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC

You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC and VAC.

Budget

$500,000

Duration

900 days

Status

600 days

EV

$180,000

PV

$150,000

AC

$178,000

BAC

?

Assume that future cost estimates are accurate and do not change.

1)ETC =

2)EAC =

3)VAC =