Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.
Calculate ETC, EAC and VAC.
Budget $3,500,000
Duration 450 days
Status 80 days
EV $500,000
PV $600,000
AC $923,000
BAC ?
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
