Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,

You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.

Calculate ETC, EAC and VAC.

Budget $3,500,000

Duration 450 days

Status 80 days

EV $500,000

PV $600,000

AC $923,000

BAC ?

Assume that future cost estimates are accurate and do not change.

1) ETC =

2) EAC =

3) VAC =