Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,

You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.

Budget

$220,000

Duration

200 days

Status

140 days

EV

$180,000

PV

$180,000

AC

$220,000

BAC

?

Assume that future cost estimates are accurate and do not change.

1) ETC =

2) EAC =

3) VAC =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!