Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC,
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
| Budget | $220,000 |
| Duration | 200 days |
| Status | 140 days |
| EV | $180,000 |
| PV | $180,000 |
| AC | $220,000 |
| BAC | ? |
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =