Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC

You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC and VAC.

Budget

$4.600,000

Duration

600 days

Status

80 days

EV

$540,000

PV

$580,000

AC

$980,000

BAC

?

Assume that the same spend rate continues

1)ETC =

2)EAC =

3)VAC =