Question: You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project.Calculate ETC, EAC and VAC.
Budget | $4.600,000 |
Duration | 600 days |
Status | 80 days |
EV | $540,000 |
PV | $580,000 |
AC | $980,000 |
BAC | ? |
Assume that the same spend rate continues
1)ETC =
2)EAC =
3)VAC =
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
