Question: Project Network: Part 1 What are the earliest start and earliest finish times for activity E? Project Network: Part 2 What's the earliest that the

Project Network: Part 1 What are the earliest

Project Network: Part 1

What are the earliest start and earliest finish times for activity E?

Project Network: Part 2

What's the earliest that the whole project could be finished?

Project Network: Part 3

What is the critical path?

Project Network: Introduction Use the following network of related activities with their duration times (in weeks) to answer the next 3 questions. A 8 D 3 Start 5 E 7 G 12 Finish B 2. F 6 10