Question: Q4. Based on the given table below, answer the questions. (25 points) Show all calculation steps in the answers Direct Costs Activiy Slope Max. Normal
Q4. Based on the given table below, answer the questions. (25 points)
Show all calculation steps in the answers
|
|
|
| Direct Costs | |||
| Activiy | Slope | Max. | Normal | Crash | ||
| ID |
| Crash Time | Time | Cost ($) | Time | Cost ($) |
| A |
|
| 6 | 110 | 3 | 170 |
| B |
|
| 7 | 160 | 3 | 280 |
| C |
|
| 13 | 120 | 10 | 210 |
| D |
|
| 15 | 120 | 11 | 240 |
| E |
|
| 6 | 200 | 4 | 230 |
| F |
|
| 11 | 80 | 7 | 180 |
| G |
|
| 8 | 120 | 5 | 240 |
CPM is A C E F G
a) Calculate the Max. crash time and slope (10 points)
b) Crash the project for 8 weeks, calculate the total cost before and after crashing (15 points)