As a project manager, youre overseeing a product launch. You meet with customers to determine the products quality standards. Then, you create processes and documentation necessary to achieve the expected quality. Which quality management concept do these tasks represent?

1 point

Quality planning

Assurance planning

Assurance standards

Quality control