Question: Question 1 : Consider the following project: table [ [ Activity , IPA,Duration ( days ) , Total cost ( $ ) ] ,

Question 1:
Consider the following project:
\table[[Activity,IPA,Duration (days),Total cost ($)],[A,---,10,100],[B,--,6,80],[C,--,3,95],[D,A,12,140],[E,B,6,65],[F,B,C,8,75],[G,E,F,18,228]]
a. Draw the activity on an arrow network for this network.
b. Draw the activity on a node network. Identify the critical path and the expected completion time.
c. Draw the Gantt chart and show the critical path on the chart.
d. Draw the cost profile for this project.
e. Solve b, c,& d using MS project
 Question 1: Consider the following project: \table[[Activity,IPA,Duration (days),Total cost ($)],[A,---,10,100],[B,--,6,80],[C,--,3,95],[D,A,12,140],[E,B,6,65],[F,B,C,8,75],[G,E,F,18,228]] a.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!