Question: Question 1 : Consider the following project: table [ [ Activity , IPA,Duration ( days ) , Total cost ( $ ) ] ,
Question :
Consider the following project:
tableActivityIPA,Duration daysTotal cost $ABCDAEBFBCGEF
a Draw the activity on an arrow network for this network.
b Draw the activity on a node network. Identify the critical path and the expected completion time.
c Draw the Gantt chart and show the critical path on the chart.
d Draw the cost profile for this project.
e Solve b c& d using MS project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
