Question: Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate Optimistic time Most Likely Pessimistic time predecessors

Question 1 The information for a project is given
Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate Optimistic time Most Likely Pessimistic time predecessors time A 2 3 4 B A 8 8 8 A 7 9 11 D A 6 6 6 E B, C 9 10 11 F 10 14 G D 6 10 14 H F, E 10 14 18 G, F 6 7 14 H1 6 8 18 7 a) Draw a network for this project b) Determine the critical path