Question: The information for a project is given in the Table below (time in weeks) : Activity Immediate predecessors Activity time (t) A - 8 B
The information for a project is given in the Table below (time in weeks):
Activity | Immediate predecessors | Activity time (t) |
A | - | 8 |
B | A | 2 |
C | A | 3 |
D | A | 60 |
E | B | 60 |
F | C | 2 |
G | D | 2 |
H | E, F | 20 |
I | G | 10 |
J | H, I | 10 |
K | J | 12 |
L | K | 3 |