Question: The information for a project is given in the Table below (time in weeks) : Activity Immediate predecessors Activity time (t) A - 8 B

The information for a project is given in the Table below (time in weeks):

Activity

Immediate predecessors

Activity time (t)

A

-

8

B

A

2

C

A

3

D

A

60

E

B

60

F

C

2

G

D

2

H

E, F

20

I

G

10

J

H, I

10

K

J

12

L

K

3

a) Draw a network for this project
b) Determine the critical path
c) Determine the earliest and latest activity times
d) Determine slack time for each activity