Question: Question 2: 2.1 Given the following data ACTIVITY PREDECESSOR DURATION(DAYS) a - 10 b - 15 c a 17 d b 5 e b 4
Question 2: 2.1 Given the following data
| ACTIVITY | PREDECESSOR | DURATION(DAYS) |
| a | - | 10 |
| b | - | 15 |
| c | a | 17 |
| d | b | 5 |
| e | b | 4 |
| f | c | 15 |
| g | d | 7 |
| h | e | 8 |
| i | f | 12 |
| j | g,h,j | 10 |
Draw the network and calculate and calculate the Critical Path: (10 MARKS)
2.2 South Africa celebrates Womens Day on the 9th August. The local government has contracted you to plan the 2020 celebration. Client specifications are as follows:
| Estimated no. of delegates | 5000 |
| Must include a lunch meal | |
| Must include 1 soft-drink per delegate | |
| Must include a Program for a day | |
| Budgeted Amount: | R1 650 000 |
Prepare a: 2.2.1 Gantt Chart (a minimum of 10 activities) (6)
2.2.2 Construct a Work Breakdown Structure (graphical format) (9)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
