Question: Question 2: 2.1 Given the following data ACTIVITY PREDECESSOR DURATION(DAYS) a - 10 b - 15 c a 17 d b 5 e b 4

Question 2: 2.1 Given the following data

ACTIVITY

PREDECESSOR DURATION(DAYS)
a - 10
b - 15
c a 17
d b 5
e b 4
f c 15
g d 7
h e 8
i f 12
j g,h,j 10

Draw the network and calculate and calculate the Critical Path: (10 MARKS)

2.2 South Africa celebrates Womens Day on the 9th August. The local government has contracted you to plan the 2020 celebration. Client specifications are as follows:

Estimated no. of delegates 5000
Must include a lunch meal
Must include 1 soft-drink per delegate
Must include a Program for a day
Budgeted Amount: R1 650 000

Prepare a: 2.2.1 Gantt Chart (a minimum of 10 activities) (6)

2.2.2 Construct a Work Breakdown Structure (graphical format) (9)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!