Question: QUESTION 2 3 If an activity whose normal duration is 1 3 days can be shortened to 1 0 days for an added cost of

QUESTION 23
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $2788, what is the crash cost per period?
 QUESTION 23 If an activity whose normal duration is 13 days