Question: Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000.
Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000.
Earned value data is available for the first three weeks of the project (see below).
The project is due to end on week 4.
| Project Data | Week 1 | Week 2 | Week 3 | Week 4 |
| Cumulative Actual Costs | $2,700 | $15,700 | $37,800 |
|
| Anticipated planned Value | $11,750 | $22,000 | $43,000 | $64,000 |
| Cumulative Earned value | $6,750 | $21,500 | $47,000 |
|
Based on the above data, calculate the following earned value indicators:
| EVM Indicator | Week 1 | Week 2 | Week 3 | Formula used |
| Cost Variance |
|
|
|
|
| Schedule Variance |
|
|
|
|
| Cost Performance Index |
|
|
|
|
| Schedule Performance Index |
|
|
|
|
| Estimated Cost At Completion (use the EAC = BAC / CPI formula) |
|
|
|
|
| Estimated Cost to Complete |
|
|
|
|
For this question you need to:
- Identify which formulas you used for each indicator;
- Show an example of your calculations (work) for each indicator; and
- Calculate each indicator for each of the first three weeks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
