Question: Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000.

Question 2: Calculate Earned Value Indicators Based on the following data: The Budget At Completion (BAC) cost of the project is estimated to be: $140,000.

Earned value data is available for the first three weeks of the project (see below).

The project is due to end on week 4.

Project Data

Week 1

Week 2

Week 3

Week 4

Cumulative Actual Costs

$2,700

$15,700

$37,800

Anticipated planned Value

$11,750

$22,000

$43,000

$64,000

Cumulative Earned value

$6,750

$21,500

$47,000

Based on the above data, calculate the following earned value indicators:

EVM Indicator

Week 1

Week 2

Week 3

Formula used

Cost Variance

Schedule Variance

Cost Performance Index

Schedule Performance Index

Estimated Cost At Completion

(use the EAC = BAC / CPI formula)

Estimated Cost to Complete

For this question you need to:

  • Identify which formulas you used for each indicator;
  • Show an example of your calculations (work) for each indicator; and
  • Calculate each indicator for each of the first three weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!