Question: Question 2 : Calculate Earned Value Indicators Based on the following data: The Budget At Completion ( BAC ) cost of the project is estimated

Question 2: Calculate Earned Value Indicators
Based on the following data:
The Budget At Completion (BAC) cost of the project is estimated to be: $52,250.
Earned value data is available for the first three weeks of the project (see below).
The project is due to end on week four (4).
Project Data Week 1 Week 2 Week 3 Week 4
Cumulative Actual Costs $5,000 $16,000 $37,800
Cumulative Planned Value $11,750 $22,000 $43,000 $52,250
Cumulative Earned Value $7,000 $22,000 $47,000
Based on the above data, calculate the following earned value indicators: