Question: Question 2 : Calculate Earned Value Indicators Based on the following data: The Budget At Completion ( BAC ) cost of the project is estimated

Question 2: Calculate Earned Value Indicators
Based on the following data:
The Budget At Completion (BAC) cost of the project is estimated to be: $52,250.
Earned value data is available for the first three weeks of the project (see below).
The project is due to end on week four (4).
Project Data Week 1 Week 2 Week 3 Week 4
Cumulative Actual Costs $5,000 $16,000 $37,800
Cumulative Planned Value $11,750 $22,000 $43,000 $52,250
Cumulative Earned Value $7,000 $22,000 $47,000
Based on the above data, calculate the following earned value indicators:
EVM Indicator Week 1 Week 2 Week 3 Formula used
Cost Variance $2000 $6000 $9200 CV=EV-AC
Schedule Variance $4750 $0 $4000 SV=EV-PV
Cost Performance Index 1.401.381.24 CPI= EV/AC
Schedule Performance Index 0.601.001.09 SPI= EV/PV
Estimated Cost At Completion
(use the EAC = BAC / CPI formula) $37,321.43 $37,898.55 $42,120.07 EAC=BAC/CPI
Estimated Cost to Complete $32,321.43 $21,898.55 $4,320.97 ETC= EAC-AC
For this question you need to:
Identify which formulas you used for each indicator;
Show an example of your calculations (work) for each indicator; and
Calculate each indicator for each of the first three weeks.
Question 3: Earned Value Management Dashboard
Based on the question 2 data, represent the projects earned value status in a visual format.
Your image need only include your AC, EV, and PV over the four-week project (see example chart at right).
This chart can be done in Excel (or equivalent), or it can be drawn by hand (and then digitally scanned or photographed, and included in your assignment).
Figure 1: Sample EVM dashboard

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!