Question: QUESTION 27 Consider the following work breakdown structure: Time Estimates (days) Most likely Pessimistic Optimistic Activity Start B Precedes A B.C D E F F

QUESTION 27 Consider the following work breakdown
QUESTION 27 Consider the following work breakdown structure: Time Estimates (days) Most likely Pessimistic Optimistic Activity Start B Precedes A B.C D E F F End 37 80 91 25 42 62 49 95 100 25 61 98 115 49 66 80 D E What is the standard deviation of path ACER 7.07 days 60 days 50 days 755 days 9.06 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!