Question: Question 7 As a project manager applying the PDCA process, you ve already attempted to fix a process that you believe is causing a common

Question 7
As a project manager applying the PDCA process, youve already attempted to fix a process that you believe is causing a common customer complaint. As your next step, you compare your results to the goal to determine if you fixed the issue. What PDCA step will you apply?
1 point
Plan
Do
Check
Act