Question: Question TASK NAME PRODECESSOR DURATION A - 3 B A 4 C A 2 D B 7 E B 6 F C 4 G D

Question

TASK NAME PRODECESSOR DURATION
A - 3
B A 4
C A 2
D B 7
E B 6
F C 4
G D 5
H E,F 2
I H 3
J G,I 4

Using the information in the network diagram created using the details above, identify the critical path tasks:

Task #1: (first task on the critical path)

Task #2: (second task on the critical path)

Task #3: (third task on the critical path)

Task #4: (fourth task on the critical path)

Task #5: (fifth task on the critical path)

What is the total length (in days) of this project's tasks?

Using the information in the network diagram, what is the Total Float / Slack available on each of these tasks:

Task C:

Task D:

Task E:

Task F:

Task H:

Task I:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!