Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days)
A 10
B 6
C 3
D B 2
E A, D 5
F C 6
G E, F 8
This exercise contains only parts b, c, and d. b)
The critical activities for the leadership training program development project are A - E - G.
c) The project length for the leadership training program development project = 23 days.
d) Slack time for each of the activities is:
Please show detail on HOW to calculate the slack time